No GST needs to be paid if the completion certificate has been received and no payment made before that.
Hope you find the information helpful if you do please rate it 5 and provide your valuable feedback for my improvement.
Thank you
Good evening sir, A Builder has entered into JDA after 01.04.2019 and commenced construction of residential house property after 01.04.2019. He opted to pay GST @ 5% without ITC under the new scheme. Does the builder have to pay GST @ 5% under the new scheme on flats booked after obtaining an Occupancy Certificate? If yes, kindly provide any reference to that
No GST needs to be paid if the completion certificate has been received and no payment made before that.
Hope you find the information helpful if you do please rate it 5 and provide your valuable feedback for my improvement.
Thank you
Dear Sir,
Hope you are doing well !!
Per Section 7 read with Schedule II of the Central Goods and Services Tax Act, 2017,
“The construction of a complex, building, civil structure or a part thereof, including a complex or building intended for sale to a buyer, wholly or partly, except where the entire consideration has been received after issuance of completion certificate, where required, by the competent authority or after its first occupation, whichever is earlier shall be treated as Supply of Service”
Once the flat is constructed and occupancy certificate is issued, the said flat is considered as Immovable Property and no GST will be levied on sale of such flat.
Hello,
If the completion certificate has been received and no payment for the flat was made before the date of the completion certificate, then no GST is leviable.
I hope this answer satisfies your requirements.
Regards,
CA Hunny Badlani